AramoniReport   
MEXICO ENERGY TENDERS
(Updated December 22, 2014)
_______________________________

ROUND-1 IN PROGRESS
_______________________________

TENDER SCHEDULE
Public notice: 11-Dec-2014
Interested pre-register: 11-Dec-2014 to 16-Mar-2015
Access to data room: 15-Jan to 14-Jul-2015
Clarifications on data room: 11-Dec-2014 to 25-Feb-2015
Prequal window: 11-Dec-2014 to 27-Apr-2015
Clarifications on prequal requirements: 11-Dec-2014 to 11-Mar-2015
Prequal ruling: 27-Apr-2015
Clarifications on tender process and contact: 28-Apr to 15-Jun-2015
Offers submission (on a block basis): 15-Jul-2015
Rulings (on a block basis): 17-Jul-2015
Termination (on a block basis): 21-Aug-2015
Further detail: info@aramoni.com
_______________________________

FYI Aramoni in association with prime French firm EOSYS (link above)
We offer local knowledge and extensive expertise for
TENDER ASSISTANCE and GEOLOGICAL ASSESSMENT services
(we will engage our already-in-place support to only one bidder)
info@aramoni.com

_______________________________

CONTRACTS (shared-production)
Block 1: light oil, 194 km2, shallow waters off South Veracruz
Block 2: light oil, 195 km2, shallow waters off South Veracruz
Block 3: light oil, 233 km2, shallow waters off South Veracruz
Block 4: light oil, 233 km2, shallow waters off South Veracruz
Block 5: light oil, 466 km2, shallow waters off West Tabasco
Block 6: light oil, 466 km2, shallow waters off West Tabasco
Block 7: light oil, 465 km2, shallow waters off center of Tabasco
Block 8: extra-heavy oil, 116 km2, shallow waters off center of Tabasco
Block 9: extra-heavy oil, 116 km2, shallow waters off center of Tabasco
Block 10: light oil, 232 km2, shallow waters off center of Tabasco
Block 11: extra-heavy oil, 309 km2, shallow waters off East Tabasco
Block 12: heavy oil, 387 km2, shallow waters off East Tabasco
Block 13: heavy oil, 501 km2, shallow waters off East Tabasco
Block 14: wet gas, 310 km2, shallow waters off West Campeche
Further detail: info@aramoni.com
_______________________________

COMING PEMEX FARM-OUTS

1. Production for shallow-water mature fields (3): Bolontiku, Sinan, Ek
2. Production for shallow-water extra-heavy oil fields (3): Ayatsil, Tekel, Utsil
3. Production for Chicontepec and non-conventional fields:
4. Production for land mature fields (3): Rodador, Ogarrio, Cardenas-Mora
5. Field development of giant deep-water gas fields (2): Kunah-Piklis
6. Field development of Perdido area (2): Trion, Exploratus

PRE-TENDER DOCS AVAILABLE SOON: info@aramoni.com

_______________________________


SPECIALIZED REPORTS

1. OFFSHORE FIXED PLATAFORMS: No Current Tenders

2. PEMEX MARINE PIPELINES

ZAAP-E to KU-A1, KMZ field, 24in x 2.8km + KU-M to ZAAP-E, KMZ field, 12in x 3.2km,
Next meeting: 29-Dec-2014
Bidders: Micoperi, Swiber, Permaducto (Protexa), Subsea7, HOC (CalDive), Dragados, Arendal, Global (Techint), Emas-AMC, Grup Servicii Petroliere, TL Offshore

KAMBESAH to IXTOC-TA, 12in x 6.5km + IXTOC-TA to IXTOC-A, 12in x 5.2km,
Next meeting: 29-Dec-2014
Bidders: Micoperi, Swiber, Permaducto (Protexa), Subsea7, HOC (CalDive), Dragados, Arendal, Global (Techint), Emas-AMC, Grup Servicii Petroliere, TL Offshore


3. LAND FLOWLINES

CFE Major Tenders

Villa de Reyes (branch), NG 276 MMCFPD
Los Ramones Line to Villa de Reyes Power Plant
Proposal submission 7-Jan-2015
Technical ruling 21-Jan-2015
Ruling 27-Jan-2015

Waha-San Elizario TX (Norte III): Gas 42in x 360km
Proposal submission 8-Jan-2015
Ruling 7-Feb-2015

Waha-Presidio TX (Ojinaga), NG 2831 MMCFPD, 42in x 230km
Proposal submission 9-Dec-2014
Ruling 8-Jan-2015

El Encino-La Laguna, NG 1500 MMCFPD, 42in x 400km
Bid proposals (investment/ tariff / PV-1 / PV-2):
Fermaca: $630.1m / $0.1222 per Gj / $602.2m / $530.1m
Enagas-Elecnor: $997.3m / $0.1610 per Gj / $756.5m / $665.9m
Transcanada: $899.6m / $0.1546 per Gj / $781.2m / $687.7m
Carso: $914.3m / $0.2073 per Gj / $965.0 / $849.5m
Sempra-IENova: $883.3m / $0.1951 per Gj / $1003.6m / $883.5m
Abengoa-China Petroleum Pipeline Berau (disqualified at technical stage)
Ruling 16-Dec-2014
Winner: Fermaca Pipeline el Encino

Ojinaga-El Encino, NG 1356 MMCFPD, 42in x 250km:
Bid proposals (investment / tariff / PV-1 / PV-2):
1. Gasoducto de Aguaprieta (Sempra-IENova): $298.9m / $0.0560 per Gj / $192.2m / $242.3m
2. Transportadora de Gas Natural del Noroeste (Transcanada): $344.6m / $0.0657 per Gj / $221.8m / $279.4m
3. Carso Energy: $323.4m / $0.0721 per Gj / $239.1m / $301.2m
4. Enagas-Elecnor: $419.8m / $0.0725 per Gj / $248.4m / $313.0m
5. Fermaca: $311.9m / $0.0749 per Gj / $250.5m / 315.6m
Omega (disqualified at technical stage)
Ruling 24-Nov-2014
Winner: Gasoducto de Aguaprieta (Sempra-IENova)

Tula (branch), NG 485 MMCFPD, 30in
Proposal submission 17-Sep-2014
Bid proposals Arendal $59.5m, ATCO $48.8m
Ruling 9-Oct-2014: ATCO


Further: info@aramoni.com
_______________________________


CURRENT KEY PROJECTS

AYATSIL-TEKEL
A Pemex RFPs just came out for
a 4.4-yr contract of well integrated services:
drilling termination and reparation
over these extra-heavy oil fields
Interested: Dowell Schlumberger, Halliburton, Weatherford, Baker Hughes, GSM, Perforadora Central

LAKACH - ONE SUBSEA
Pemex awarded to Schlumberger-Cameron
a $270m contract to supply, install and
commission a 7-well production
system for the Lakash deepwater
giant gas field

LAKACH - SAIPEM
An EPCI contract for gas field development
at 850 to 1200-meter water depth
was awarded by Pemex to Saipem
Scope includes:
Two 73-km long 18-in diameter flowlines
Main umbilical 50-km long
SURF works

_______________________________


Next