PROJECT TRACKER   (2 of 2)

IN CONSTRUCTION


PEMEX EXPLORATION & PRODUCTION (PEP)

OFFSHORE PLATFORM HISTORY

45. Kab-A [AWARDED]
Project
Light structure platform
Scope: Engineering/ procurement/ construction/ loading/ fixing
Location: Campeche basin GOM
Term: 210 days starting 30.Aug.07
Mailstones:
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $3m+
Contract
Type: Lump sum & unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Local content:
Subcontracts allowed:
Bid follow-up
Ref: 18575106-022-07
Release: 31.May.07
Site visit: n/a
1st clarification meeting: 14.Jun.07
4th clarification meeting: 16.Jul.07 (last)
Closing: 18.Jul.07
Submission & opening: 24.Jul.07
Decision: 08.Aug.07
Registered bidders
1.Industria del Hierro (ICA Fluor Daniel) 2.Construcciones Mecanicas Monclova (COMMSA-GIMSA) 3.Swecomex 4.J Ray McDermott 5.Dragados 6.Grupo Constructor Global 7.Construcciones y Equipos Latinoamericanos (Protexa) 8.CIT
Status AWARDED
Decision: 28.Aug.07
Industria del Hierro (ICA Fluor Daniel): $9.5million
Updated 07.Sep-07

44. Atun-D [AWARDED]
Project
Gathering platform
Scope: Construction
Location: Offshore Tuxpan Veracruz
Term: 329 days starting 10.Aug.07
Mailstones:
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $5.5m+
Contract
Type: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Local content:
Subcontracts allowed:
Bid follow-up
Ref: 18575106-010-07
Release: 10.May.07
Site visit: n/a
1st clarification meeting: 24.May.07
6th clarification meeting: 26.Jun.07 (last)
Closing: 29.Jun.07
Submission & opening: 05.Jul.07
Registered bidders
1.CIT 2.Construcciones Mecanicas Monclova (COMMSA-GIMSA) 3.Construcciones y Equipos Latinoamericanos (Protexa) 4.Dragados 5.Industria del Hierro (ICA Fluor Daniel) 6.J Ray Mcdermott 7.Swecomex 8.Shaw 9.Oceanografia 10.ABB 11.Grupo Constructor Global
Potential participants
Status AWARDED
Decision: 20.Jul.07
Construcciones Mecanicas Monclova (COMMSA-GIMSA): $19million
Updated 31.Jul.07

43. Sinan-118 [AWARDED]
Project
Light structure platform
Scope: Engineering/ procurement/ construction/ loading/ fixing
Location: Campeche basin GOM
Term: 210 days starting 01.Aug.07
Mailstones:
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $3.25m+
Contract
Type: Lump sum & unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Local content:
Subcontracts allowed:
Bid follow-up
Ref: 18575106-020-07
Release: 26.Apr.07
Site visit: n/a
1st clarification meeting: 11.May.07
4th clarification meeting: 14.Jun.07 (last)
Closing: 14.Jun.07
Submission & opening: 20.Jun.07
Registered bidders
1.Construcciones Mecanicas Monclova (COMMSA-GIMSA) 2.Industria del Hierro (ICA Fluor Daniel) 3.Dragados 4.Bosnor 5.Shaw 6.Swecomex 7.Construcciones y Equipos Latinoamericanos (Protexa) 8.ICS Triplex 9.JA Energy Fab
Potential participants
CIT. Evya
Status AWARDED
Decision: 20.Jul.07
Construcciones Mecanicas Monclova (COMMSA-GIMSA): $11million
Updated 31.Jul.07

42. Sinan-So [AWARDED]
Project
Light structure platform
Scope: Engineering/ procurement/ construction/ loading/ fixing
Location: Campeche basin GOM
Term: 210 days starting 30.Jul.07
Mailstones:
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $3.75m+
Contract
Type: Lump sum & unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Local content:
Subcontracts allowed:
Bid follow-up
Ref: 18575106-019-07
Release: 17.Apr.07
Site visit: n/a
1st clarification meeting: 30.Apr.07
6th clarification meeting: 05.Jun.07
Closing: 07.Jun.07
Submission & opening: 13.Jun.07
Registered bidders
1.Bosnor 2.Dragados 3.Construcciones Mecanicas Monclova (COMMSA-GIMSA) 4.Construcciones y Equipos Latinoamericanos (Protexa) 5.Tradeco 6.Industria del Hierro (ICA Fluor Daniel) 7.Shaw 8.Swecomex 9.CIT 10.ICS Triplex
Potential participants
Grupo Constructor Global, INCYQ, Evya
Status AWARDED
Decision: 20.Jul.07
Swecomex: $12million
Updated 31.Jul.07

41. Yaxche-B [AWARDED]
Project
Light structure platform
Scope: Engineering/ procurement/ construction/ loading/ fixing
Location: Campeche basin GOM
Term: 210 days starting 17.Jul.07
Mailstones:
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $3.25m+
Contract
Type: Lump sum & unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Local content:
Subcontracts allowed:
Bid follow-up
Ref: 18575106-017-07
Release: 03.Apr.07
Site visit: n/a
1st clarification meeting: 23.Apr.07
4th clarification meeting: 28.May.07
Closing: 30.May.07
Submission & opening: 05.Jun.07
Registered bidders
1.Bosnor 2.Construcciones Mecanicas Monclova (COMMSA-GIMSA) 3.Grupo Constructor Global 4.Industria del Hierro (ICA Fluor Daniel) 5.J Ray McDermott 6.Shaw 7.Dragados 8.CIT 9.Tradeco 10.Construcciones y Equipos Latinoamericanos (Protexa) 11.Swecomex 12.ICS Triplex
Potential participants
Industrias W, INCYQ
Status AWARDED
Decision: 19.Jul.07
Industria del Hierro (ICA Fluor Daniel): $11.5million
Updated 31.Jul.07

40. HA-LT-01: Living quarter module [VOID]
Project
187 living quarter module & interconnection bridge
Scope: Engineering/ procurement/ construction/ loading/ fixing/ transport/ installation
Location: Campeche basin GOM
Term: 660 days starting 01.Aug.07
Mailstones:
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $20m+
Contract
Type: Lump sum & unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Local content:
Subcontracts allowed:
Bid follow-up
Ref: 18575106-013-07
Release: 29.Mar.07
Site visit: 12.Apr.07
1st clarification meeting: 17.Apr.07
8th clarification meeting: 29.May.07
Closing: 29.May.07
Submission & opening: 04.Jun.07
Registered bidders
1.Dragados 2.Industria del Hierro (ICA Fluor Daniel) 3.Swecomex 4.Grupo Constructor Global 5.JA Energy Fab 6.Tradeco 7.Construcciones Mecanicas Monclova (COMMSA-GIMSA) 8.Evya 9.Keppel SLP 10.Ingelectric
Potential participants
SIDO E, GI, AILT, Industrias W, Alcatel, Swath, AVC, Heerema
Status VOID
Tender ruled on 19.Jul.07
A new RFP to be released shortly
Updated 31.Jul.07

___________________________________

FYI, we have got a comprehensive
understanding of these tenders and
offer expert tailor-made assistance to
international companies pursuing projects in Mexico
A description of our services in the bottom page
Contact: mail@aramoni.com
____________________________________


39. Tumut-A: Tetrapod [AWARDED]
Project
Offshore terapod platform
Scope: Engineering/ procurement/ construction/ loading/ fixing
Location: Campeche basin GOM
Term: 330 days starting 13.Jul.07
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $9m+
Contract
Type: Lump sum & unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Local content:
Subcontracts allowed:
Bid follow-up
Ref: 18575106-009-07
Release: 27.Mar.07
Site visit: n/a
1st clarification meeting: 13.Apr.07
6th clarification meeting: 25.May.07
Closing: 26.May.07
Submission & opening: 01.Jun.07
Registered bidders
1.Swecomex 2.Industria del Hierro (ICA Fluor Daniel) 3.Dragados 4.Construcciones Mecanicas Monclova (COMMSA-GIMSA) 5.Construcciones y Equipos Latinoamericanos (Protexa) 6.Bosnor 7.Shaw 8.J Ray Mcdermott
9.CIT 10.Grupo Constructor Global 11.Tradeco
Potential participants
Industrias W, INCYQ, Ardica
Status AWARDED
Decision: 12.Jul.07
Construcciones Mecanicas Monclova (COMMSA-GIMSA): $24million
Updated 31.Jul.07

38. HA-RE-01: LIVING QUARTER MODULE (2nd round) [VOID]
Project
150 living quarter module & interconnection bridge
Scope: Engineering/ procurement/ construction/ loading/ fixing/ transport/ installation/ interconnection/ testing/ commissioning/ start-up
Location: Rebombeo (re-pumping) complex
Field: Campeche basin GOM
Term: 570 days starting 21.Aug.07
Mailstones:
Living module 480 days
Transport 510 days
Start-up 570 days
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $9m+
Contract
Type: Lump sum & unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Local content:
Subcontracts allowed:
Bid follow-up
Ref: 18575106-036-06
Release: 26.Dec.06
Site visit: 03.Jan.07
1st clarification meeting: 04.Jan.07
15th clarification meeting: 25.May.07
Closing: 29.May.07
Submission & opening: 04.Jun.07
Decision: 22.Jun.07 (next)
Registered bidders
1.Construcciones Mecanicas de Monclova (GIMSA-COMMSA) 2.Bosnor 3.Swecomex 4.Grupo Constructor Global 5.CIT 6.Ingelectric Norteamerica 7.Industria del Hierro (ICA Fluor Daniel) 8.Dragados 9.CIMISA
Potential participants
Global Offshore, C&M Marine Services USA Heerema Marine Contractors, Teleconstrucciones Mexicanas, Alcatel
Bidders for 1st round
1.Construcciones Mecanicas de Monclova (GIMSA-COMMSA) 2.DMI International 3.Swecomex 4.AR del Golfo 5.Industria del Hierro (ICA Fluor Daniel) 6.CIMISA 7.Keppel SLP 8.Lonestar Marine Shelters 9.Dragados 10.Kepler Constructora
Status VOID
Tender ruled on 19.Jul.07
A new RFP to be released shortly
Updated 31.Jul.07

CHEMUL: Underwater Platform [VOID]
Project
Scope: Katrina’s damage repair & platform full refurbishment
Current location: Atlantic Marine dockyard, Mobile AL
Service location: Contractor’s facilities
Contract
Commissioner: Pemex (Govt)
Type: Unit prices
Term: 435 days
Payments: 30 days after invoice procedures
Selection basis: Best qualified amongst compliant proposals
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Bid follow-up
Ref: 18575107-091-06
Release: 16.Nov.06
Site visit (Atlantic Marine dockyard, Mobile AL): 27.Nov.06
1st clarification meeting (Ciudad del Carmen Campeche): 05.Dec.06
7th meeting & closing: 02.Feb.07
Submission & opening: 08.Feb.07
Registered bidders (not comprehensive)
1.Cotemar 2.KSES USA 3.OIS
Potential participant
Halliburton
Status VOID
Tender ruled on 08.Feb.07
A new RFPs to be announced shortly
Updated 25.May.07

PLATFORM COMPLEMENTARY WORKS (2nd-round) [AWARDED]
Project
Term: 365 days starting 26.Jan.07
Local content: 30%
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Experience: 5 yrs
Combine equity: $45m+
Subcontracts allowed: Catering & accomodation/ X-rays/ ultrasonic inspection/ diving
Contract
Type: Unit prices
Down payment: n/a
Payments: 30 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bid follow-up
Ref: 18575108-084-06
Release: 26.Sep.06
Site visit: 09.Oct.06
8th clarification meeting: 08.Dec.06 (last)
Closing: 08.Dec.06
Submission & opening: 14.Dec.06
Registered bidders
1.Condux (Protexa) 2.Construcciones Integrales del Carmen 3.Diavaz 4.Cotemar 5.Global Offshore 6.Mantenimiento Marino de Mexico (Halliburton) 7.Oceanografia 8.Tradeco
Bidders in 1st round
Oceanografia, Condux (Protexa), Construcciones Integrales del Carmen, Cotemar, Tradeco
Decision: 15.Jan.07
Finalizing: 25.Jan.07
Status AWARDED
Oceanografia: $47million
(Updated 19.Jan.07)

37. HA-CA-01: LIVING QUARTER MODULE [AWARDED]
Project
1. Existing module uninstallation
Scope: Engineering/ dismantlement/ loading/
fixing/ maritime transport/ unloading in
Dos Bocas terminal (Tabasco)/ transport/
final disposition
2. New 150 living module
Scope: Engineering/ procurement/
construction/ testing/ loading/ fixing/
transport/ installation on existing structure
located in Cayo Arcas (Campeche basin)/
interconnection/ commissioning/ start-up
Field: Campeche basin
Term: 570 days starting 18.Oct.06
Bidders profile
Company/consortium from countries having a
free trade agreement with Mexico
Combine equity: $9m+
Subcontracts allowed:
Ships/ offshore catering/ accommodation/
X-rays/ NDT/ radio positioning
Contract
Type: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bid follow-up
Ref: 18575106-011-06
Release: 20.Apr.06
Submission & opening: 04.Sep.06
Decision: 25.Oct.06
Registered bidders: 1.Construcciones Mecanicas de Monclova (GIMSA-COMMSA) 2.Swecomex 3.Industria del Hierro (ICA Fluor Daniel) 4.Construccion Ingenieria y Montaje Integral (CIMISA) 5.Lonestar Marine Shelters 6.GOIMAR 7.Dragados Offshore de Mexico 8.Keppel-SLP 9.AR del Golfo
Status AWARDED
Industria del Hierro (ICA Fluor Daniel): $90million
(Updated 02.Nov.06)

LIVING QUARTER MODULE [CANCELED]
Project
151 living module
Scope: Civil & electromechanical works/ superstructure/ heliport/ interconnection bridge
Location: Rebombeo complex
Field: Campeche basin
Term: 600 days starting 18.Oct.06
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $6.5m+
Contract
Type: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Local content: 51%
Subcontracts allowed: X-rays/ NDT/ project certification
Bid follow-up
Ref: 18575108-039-06
Release: 20.Jun.06
Registered bidders: 1.Construcciones Mecanicas de Monclova (GIMSA-COMMSA) 2.DMI International 3.Swecomex 4.AR del Golfo 5.Industria del Hierro (ICA Fluor Daniel) 6.CIMISA 7.Keppel SLP 8.Lonestar Marine Shelters 9.Dragados 10.Kepler Constructora
Decision: 15.Aug.06: CANCELED
A 2nd-round tender to be announced next year
(Updated 19.Aug.06)

Platform conclusion [VOID]
Project
Equipment related assignments
Scope: EPC
Platforms: AKAL complex
Field: Campeche basin
Term: 452 days from 22.Jun.06 to 02.Sep.07
Bidders profile:
Company/consortium from countries having a
free trade agreement with Mexico
Combine equity: $12m+
Subcontracts allowed: Hot-tapping/ X-rays/
NDT/ PLC setting/ FM-200/ CO2/
offshore catering & accommodation/
satellite positioning/ diving/ risk analysis
Contract:
Type: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from
compliant proposals
Bid follow-up:
Ref: 18575106-008-06
Release: 23.Mar.06
Deadline: 18.May.06
Submission & opening: 24.May.06
Registered bidders: 1.Diavaz 2.Demar 3.Dragados 4.Construcciones Integrales del Carmen 5.Condux (Protexa) 6.Oceanografia 7.Lico Construcciones 8.AR del Golfo 9.GOIMSA
Decision: 08.Jun.06: VOID
A 2nd-round tender to be announced soon
(Updated 16.Jun.06)

Platform linking [AWARDED]
Project
Platform interconnections:
PB-KU-M & HA-KU-M
PB-KU-M & PP-KU-M
PB-KU-S & HA-KU-S
PB-KU-S & PP-KU-S
PP-KU-S & PP-KU-G
PP-KU-S & PP-KU-G
PP-KU-A2 & HA-ZAAP-C
PP-KU-A2 & PP-ZAAP-C
Pipes:
PP-ZAAP-B to PB-ZAAP-C: Oil 24” 2.4 Km
E-KU-A2 to CA-AC-2: Gas 36” 16.8 Km
PI-AC-1 A PP-KU-S: Nitrogen 36” 17.2 Km
PB-KU-S A PP-KU-M: Nitrogene 24” 6.4 Km
PB-KU-S A PP-ZAAP-C: Nitrogene 24” 14 Km
Scope: EPC
Field: Ku-Maloob-Zaap
Term: 270 days from 25.May.06 to 18.Feb.07
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $8.5m+
Subcontracts allowed: Ships/ hot-tapping/ X-rays/ NDT/ PLC setting/ FM-200/ CO2/ offshore catering & accommodation/ satellite positioning/ diving/ risk analysis
Contract
Type: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bid follow-up
Ref: 18575106-007-06
Release: 16.Mar.06
Submission & opening: 20.Apr.06
Registered bidders: 1.Diavaz 2.Demar 3.Oceanografia 4.Condux (Protexa) 5.Jantesa 6.ARB Arendal 7.GOIMSA 8.Construcciones Integrales del Carmen 9.Dragados
Decision: 10.May.06
Demar Instaladora y Constructora: $40million
(Updated 12.May.06)

36. HA-AJ-01:Living quarter module [AWARDED]
Project
1. Existing module uninstallation
Scope: Engineering/ dismantle/ loading/ fixing/ maritime transport/ unloading in Dos Bocas terminal (Tabasco)/ transport/ final disposition
2. New 84 living module
Scope: Engineering/ procurement/ construction/ testing/ loading/ fixing/ transport/ installation/ interconnection/ commissioning/ start-up
Field: Cantarell
Term: 570 days from 30.Jan.06 to 22.Aug.07
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $10m+
Subcontracts allowed: Ships/ offshore catering/ accommodation/ diving/ transport & crane in Dos Bocas terminal
Contract:
Type: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bid follow-up:
Ref: 18575106-027-05
Release: 30.Aug.05
Submission & opening: 14.Dec.05
Registered bidders (not comprehensive): 1.Construcciones y Equipos Latinoamericanos (CELASA-PROTEXA) 2.Swecomex 3.Dragados Offshore Mexico 4.Siemens 5.Construcciones Mecanicas de Monclova (GIMSA-COMMSA) 6.Bosnor 7.Lonestar Marine Shelters 8.Farmadule Emtunga AB 9.Bay Inelectra de Mexico 10.ESPL Optima 11.Delta Engineering Corp 12.Keppel SLP 13.CIMISA 14.Industria del Hierro (ICA Fluor Daniel)
Decision: 25.Jan.06
Swecomex: $60million
(Updated 09.Feb.06)

FPSO Supervision Service (2nd round) [AWARDED]
Scope:
Technical assistance & supervision for engineering/ procurement/ construction/ installation/ testing/ commissioning &
start-up of an FPSO in the GOM
Term: from Nov-05 to Jul-07
Working place: Norway, UAE, Singapore/ US/ Sweden/ Spain & China
Selection basis:
Lowest price bid from qualified proposals
Bid follow-up:
Ref: 18200002-020-05
Release: 24.Nov.05
Submission & offers disclosure: 21.Dec.05
Registered bidders: 1.Intec Engineering (US) 2.Global Project Consultants (US) 3.Cygnus Industrial 4.SGS 5.Bureau Veritas
Decision: 09.Jan.06
Cygnus Industrial: $3.64million
(Updated 20.Jan.06)

35. Carpa-B (Gathering) [AWARDED]
Project description
Technical: Gathering platform
Location: Poza Rica-Altamira
Scope: Engineering/ procurement/ fabrication/ installation
Term: 333 days from 21-Jul-05
Contracts: Unit prices
Down payment: n/a
Payments: 30 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $9m+
Subcontracts allowed: Engineering/ risk analysis/ certification/ sub-inspection/ non-destructive testing/ transport/ installation
Bid follow-up:
Ref: 18575008-012-05
Release: 10-Mar-05
Registration deadline: 20-May-05
Submission: 26-May-05
Registered bidders (not comprehensive): 1.Swecomex 2.Shaw Mexican Holdings 3.Construcciones y Equipos Latinoamericanos (PROTEXA) 4.Stolt Offshore 5.Evya 6.Industria del Hierro (ICA) 7.Construccion Ingenieria y Montaje Integral (CIMISA)
Offers disclosure: 10-Jun-05
Decision: 22-Jul-05
Shaw Mexican Holdings $23million

34. Bagre-C (Gathering) [AWARDED]
Project description
Technical: Gathering platform
Location: Poza Rica-Altamira
Scope: Engineering/ procurement/ fabrication/ installation
Term: 330 days from 09-May-05
Contracts: Unit prices
Down payment: n/a
Payments: 30 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $9m+
Subcontracts allowed: Engineering/ risk analysis/ certification/ sub-inspection/ non-destructive testing/ transport/ installation
82Bid follow-up:
Ref: 18575008-082-04
Release: 28-Dec-04
Submission: 15-Mar-05
Registered bidders: 1.Construcciones y Equipos Latinoamericanos (PROTEXA) 2.Industria del Hierro (ICA) 3.Evya 4.Shaw Mexican Holdings 5.COMINTER 6.CIMISA 7.Swecomex 8.Abengoa Mexico 9.Stolt Offshore
Offers disclosure: 30-Mar-05
Decision: 11-May-05
SIPHNOS $15.6million
(Updated 20-May-05)

a. Offshore transport & installation [VOID]
Project description
Scope/ location: Transport from fabrication yards/ installation in Campeche basin GOM
Platforms included:
Drill: PP-KU-S, PP-ZAAP-A/B/D, PP-CITAM-A, PP-SIHIL-A & PP-AKAL-Q/W
Production: PB-KU-M, PB-KU-S, PB-KU-A2 & PB-KU-H
Living quarters: HA-KU-M/S/H & HA-ZAAP-C
Term: 597 days from 07-May-05
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $30m+
Subcontracts allowed: Ship services/ x-ray inspection/ non-destructive testing/ engineering/ diving/ satellite positioning/ ROV/ grommets-chackles-lift frames
Bid follow-up:
Ref: 18575106-047-04
Release: 30-Dec-04
Registration deadline: 11-Mar-05
Submission: 17-Mar-05
Registered bidders: 1.Heerema Marine Contractors Mexico 2.Condux (PROTEXA) 3.Cotemar 4.Servicios Maritimos de Campeche 5.Maritima Mexicana (TMM) 6.Oceanografia 7.Saipem 8.Global Offshore Mexico
Offers disclosure: 05-Apr-05
Decision: 22-Apr-05
VOID
(Updated 25-Apr-05)

33. PP-AKAL-W (Drill)
Project description
Technical: 8-leg drilling platform
Location: Field Cantarell Campeche basin
Scope: Procurement/ fabrication/ testing/ loading/ fixing
Term: 450 days from 20-Dec-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $7.3m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-042-04
Release: 05-Oct-04
Submission: 02-Dec-04
Registered bidders: 1.Industria del Hierro (ICA Fluor Daniel) 2.Dragados Offshore de Mexico 3.Berry Contracting 4.Shaw Mexican Holdings 5.Swecomex 6.Evya 7.Bosnor 8.Construcciones Mecanicas de Monclova (COMMSA) 9.Construcciones y Equipos Lationamericanos CELASA (Protexa) 10.COMINTER 11.Kiewit Offshore Services 12.Construccion Ingenieria y Montaje Integral (CIMISA) 13.Abengoa Mexico
Offers disclosure: 10-Dec-04
Decision: 10-Jan-05
Construcciones Mecanicas de Monclova (COMMSA-GIMSA): $39.5million
(Updated 28-Jan-05)

32. PP-AKAL-Q (Drill)
Project description
Technical: 8-leg drilling platform
Location: Field Cantarell Campeche basin
Scope: Procurement/ fabrication/ testing/ loading/ fixing
Term: 450 days from 20-Dec-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $7.3m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-041-04
Release: 05-Oct-04
Submission: 23-Nov-04
Registered bidders: 1.Industria del Hierro (ICA Fluor Daniel) 2.Dragados Offshore de Mexico 3.Berry Contracting 4.Shaw Mexican Holdings 5.Swecomex 6.Evya 7.Bosnor 8.Construcciones y Equipos Latinoamericanos CELASA (PROTEXA) 9.Construcciones Mecanicas de Monclova (COMMSA) 10.COMINTER 11.Kiewit Offshore Services 12.Abengoa Mexico 13.Delta Engineering Corp 14.Construccion Ingenieria y Montaje Integral (CIMISA)
Decision: 17-Dec-04
Construcciones Mecanicas de Monclova (COMMSA-GIMSA): $40million
(Updated 28-Jan-05)

31. PP-SIHIL-A (Drill)
Project description
Technical: 8-leg drilling platform
Location: Block Sihil Campeche basin
Scope: Procurement/ fabrication/ testing/ loading/ fixing
Term: 450 days from 20-Dec-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $7.3m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-040-04
Release: 05-Oct-04
Submission: 16-Nov-04
Registered bidders: 1.Industria del Hierro (ICA Fluor Daniel) 2.Dragados Offshore de Mexico 3.Berry Contracting 4.Shaw Mexican Holdings 5.Swecomex 6.Evya 7.Bosnor 8.Construcciones y Equipos Latinoamericanos CELASA (PROTEXA) 9.Construcciones Mecanicas de Monclova (COMMSA) 10.COMINTER 11.Kiewit Offshore Services 12.Obras Portuarias de Coatz 13.Nautica Saltamar
Decision: 14-Dec-04
Construcciones Mecanicas de Monclova (COMMSA-GIMSA): $36.5million
(Updated 28-Jan-05)

30. PB-KU-H (Production)
Project description
Field: Ku-Maloob-Zaap
Scope: Engineering/ procurement/ fabrication/ yard testing/ loading/ fixing/ technical assistance for installation/ testing/ commissioning/ start-up
Term: 790 days from 25-Nov-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $22m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-022-04
Release: 08-Jun-04
Submission: 06-Oct-04
Registered bidders: 1.Industria del Hierro (ICA Fluor Daniel) 2.Swecomex 3.Construcciones y Equipos Latinoamericanos (PROTEXA) 4.Maritima Petroleo e Ingenieria de Mexico 5.Turbinas Solar 6.Bosnor 7.Dynamic Industries 8.Odebrecht Oil & Gas Mexico 9.Kiewit Offshore Services 10.Dragados Offshore de Mexico
Decision: 24-Nov-04
Bosnor: $162million
(Updated 29-Nov-04)

28/29. HA-KU-H & ZAAP-C (Living quarters)
Project
Description: 2x220 offshore living quarters including piles sub/superstructures living modules heliport & operational systems
Field: Ku-Maloob-Zaap
Scope: Engineering/ procurement/ fabrication/ yard testing/ loading/ fixing/ technical assistance for installation/ interconnections/ commissioning/ start-up
Term: 663 days from 02-Dec-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $21m+
Subcontracts allowed: HAZOP/ IPR/ marine services/ X-rays/ non-destructive testing/ engineering/ model/ weighing
Bid follow-up:
Ref: 18575106-027-04
Release: 17-Jun-04
Submission: 22-Oct-04
Registered bidders: 1.SLP Engineering 2.Alianz Petroleum 3.Swecomex 4.Delta Engineering Corporation 5.Construcciones y Equipos Latinoamericanos (PROTEXA) 6.Construcciones Mecanicas de Monclova (COMMSA) 7.Bam Steel Structures 8.Odebrecht Oil & Gas Mexico 9.Berry Contracting 10.Bosnor - Leirvik Module Technology 11.Dynamic Industries 12.Dragados Offshore de Mexico 13.Constructora Bay de Mexico 14.Emtunga 15.CELASA (PROTEXA) 16.Keppel Offshore & Marine 17.Swecomex 18.Technip Offshore 19.Maritima Petroleo e Ingenieria de Mexico
Decision: 10-Dec-04
Berry Contracting - Berry GP - Inelectra: $149million
(Updated 12-Dec-04)

26/27. HA-KU-S & M (Living quarters)
Project
Description: 2x220 offshore living quarters including piles sub/superstructures living modules heliport & operational systems
Field: Ku-Maloob-Zaap
Scope: Engineering/ procurement/ fabrication/ yard testing/ loading/ fixing/ technical assistance for installation/ interconnections/ commissioning/ start-up
Term: 663 days from 08-Nov-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $25m+
Subcontracts allowed: HAZOP/ IPR/ marine services/ X-rays/ non-destructive testing/ engineering/ model/ weighing
Bid follow-up:
Ref: 18575106-025-04
Release: 03-Jun-04
Registration deadline: 16-Sep-04
Submission: 22-Sep-04
Registered bidders: 1.SLP Engineering 2.Technip Offshore 3.Dragados Offshore Mexico 4.Condux 5.Swecomex 6.Construcciones y Equipos Latinoamericanos (PROTEXA) 7.Alianz Petroleum 8.Delta Engineering Corporation 9.Bam Steel Structures 10.Bosnor 11.Dynamic Industries 12.Keppel Offshore & Marine USA 13.Emtunga 14.Construcciones Maritimas y Terrestres de Tabasco 15.Constructora Bay de Mexico 16.Leirvik Beacom Maritime 17.Maritima Petroleo e Ingenieria de Mexico 18.Odebrecht Oil & Gas Mexico 19.Berry Contracting
Offers disclosure: 07-Oct-04
Decision: 29.Oct.04
Keppel Offshore and Marine USA - SLP Engineering Limited - Anfels - Gulf Island: $164million

25. CITAM-A (4-legs)
Project
Scope: Engineering/ procurement/ fabrication/ loading/ fixing
Term: 365 days from 20-Sep-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $2.5m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-020-04
Release: 03-Jun-04
Submission: 29-Jul-04
Registered bidders (not comprehensive): 1.Constructora Bay de Mexico 2.Construcciones Mecanicas de Monclova (COMMSA) 3.Swecomex 4.Construcciones y Equipos Latinoamericanos (PROTEXA) 5.COMINTER 6.Shaw Global Energy Services-Shaw Mexican Holdings 7.Bosnor 8.Cominter 9.Berry Contracting
Offers disclosure: 13-Aug-04
Decision: 01-Sep-04
Construcciones y Equipos Latinoamericanos (PROTEXA) $24million

24. CB-ZAAP-C (Compression)
Project
Description: Compression platform/ bridge to production PB-ZAAP-C
Field: Ku-Maloob-Zaap
Scope: Engineering/ procurement/ fabrication/ loading/ fixing/ technical assistance for installation/ interconnections/ commissioning/ start-up
Term: 810 days from 05-Nov-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $20.5m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-017-04
Release: 06-May-04
Registration deadline: 17-Sep-04
Submission: 23-Sep-04
Registered bidders: 1.Construcciones y Equipos Latinoamericanos (PROTEXA) 2.Industria del Hierro (ICA Fluor Daniel) 3.Maritima Petroleo e Ingenieria de Mexico 4.Swecomex 5.Keppel Offshore & Marine USA 6.Kiewit Offshore Services 7.Nuovo Pignone 8.Bosnor 9.Tubinas Solar 10.Dragados Offshore Mexico
Offers disclosure: 05-Oct-04
Decision: Cancelled

23. PB-ZAAP-C (Link/production)
Project
Description: Link/production platform/ burner/ bridge to drilling PP-ZAAP-C/ bridge to new living-quarter HA-ZAAP-C/ bridge & 2 tripods to burner
Field: Ku-Maloob-Zaap
Scope: Engineering/ procurement/ fabrication/ loading/ fixing/ technical assistance for installation/ interconnections/ commissioning/ start-up
Term: 790 days from 01-Nov-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $19.5m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-016-04
Release: 06-May-04
Registration deadline: 08-Sep-04
Submission: 14-Sep-04
Registered bidders (not comprehensive): 1.Izar Construcciones 2.Construcciones y Equipos Latinoamericanos (PROTEXA) 3.Industria del Hierro (ICA Fluor Daniel) 4.Turbinas Solar 5.Constructora Bay de Mexico 6.Bosnor 7.Dragados Offshore de Mexico 8.Maritima Petroleo e Ingenieria de Mexico 9.Swecomex 10.Keppel Offshore & Marine USA 11.Kiewit Offshore Services 12.Nuovo Pignone
Offers disclosure: 24-Sep-04
Decision: Cancelled

22. PP-Zaap-A (Drill)
Project
Field: Ku-Maloob-Zaap
Scope: Engineering/ procurement/ fabrication/ loading/ fixing/ technical assistance for installation
Term: 450 days from 20-May-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $6m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-005-04
Release: 29-Jan-04
Submission: 29-Mar-04
Registered bidders (not comprehensive): 1.Industria del Hierro 2.Construcciones y Equipos Latinoamericanos (PROTEXA) 3.Constructora Bay de Mexico 4.Bosnor 5.Construccion Ingenieria y Montaje Integral (CIMISA) 6.Swecomex 7.Maritima Petroleo e Ingenieria de Mexico 8.Swath de Mexico
Offers disclosure: 19-Apr-04
Decision: 07.May.04
ICA Fluor Daniel: $43million

21. PP-Zaap-B (Drill)
Project
Field: Ku-Maloob-Zaap
Scope: Engineering/ procurement/ fabrication/ loading/ fixing/ technical assistance for installation
Term: 450 days from 21-May-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $5.5m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-006-04
Release: 29-Jan-04
Registration deadline: 25-Mar-04
Submission: 31-Mar-04
Registered bidders: 1.Industria del Hierro 2.Construcciones y Equipos Latinoamericanos (PROTEXA) 3.Bosnor 4.Construccion Ingenieria y Montaje Integral (CIMISA) 5.Swecomex 6.Maritima Petroleo e Ingenieria de Mexico 7.Swath de Mexico 8.Constructora Bay de Mexico
Offers disclosure: 20-Apr-04
Decision: 21.May.04
Industria del Hierro (ICA Fluor Daniel): $39million

20. PP-Zaap-D (Drill)
Project
Field: Ku-Maloob-Zaap
Scope: Engineering/ procurement/ fabrication/ loading/ fixing/ technical assistance for installation
Term: 450 days from 24-May-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $5.7m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-007-04
Release: 29-Jan-04
Registration deadline: 27-Mar-04
Submission: 02-Abr-04
Registered bidders: 1.Industria del Hierro 2.Construcciones y Equipos Latinoamericanos (PROTEXA) 3.Constructora Bay de Mexico 4.Dragados Offshore de Mexico 5.Bosnor 6.Swecomex 7.Construccion Ingenieria y Montaje Integral (CIMISA) 8.Maritima Petroleo e Ingenieria de Mexico 9.Swath de Mexico
Offers disclosure: 22-Apr-04
Decision: 21.May.04
Industria del Hierro (ICA Fluor Daniel): $42million

19. PP-KU-S (Drill)
Project
Field: Ku-Maloob-Zaap
Project: Drill platform/ bridge to PP-KU-G (in place)
Scope: Engineering/ procurement/ fabrication/ loading/ fixing/ technical assistance for installation
Term: 450 days from 08-May-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $5.5m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-002-04
Release: 22-Jan-04
Submission: 22-Mar-04
Registered bidders: 1.Dragados Offshore de Mexico 2.Industria del Hierro 3.Construcciones y Equipos Latinoamericanos (PROTEXA) 4.Bosnor 5.Constructora Bay de Mexico 6.Swecomex 7.Construccion Ingenieria y Montaje Integral (CIMISA) 8.Kiewit Offshore Services
Offers disclosure: 05-Apr-04
Decision: 07.May.04
Industria del Hierro (ICA Fluor Daniel): $45million

18. YAXCHE-A (8L-Drill) [AWARDED]
Scope: Engineering/ procurement/ construction/ loading/ fixing
Term/ field/ location: 300 days from 02-Apr-04/ Tabasco littoral/ Gulf of Mexico
Bid follow-up:
Ref: 18575106-010-03
Release: 30-Dec-03
Bidders:
1.Construcciones y Equipos Latinoamericanos (PROTEXA) 2.Bosnor 3.Construccion Ingenieria y Montaje Integral (CIMISA) 4.Swecomex 5.COMINTER
Decision: 22-Mar-04
COMINTER $22.5 million
(Updated 26-Mar-04)

17. PB-KU-M (Production)
Project: Production platform/ burner/ bridge to drilling PP-KU-M (in place)/ bridge to living-quarter HA-KU-M (to be tendered)/ bridge & tripod to burner in KMZ field
Original scope: Engineering/ procurement/ fabrication/ loading/ transport/ installation/ interconnection/ commissioning/ start-up
Actual scope: Engineering/ procurement/ fabrication/ loading/ technical assistance for installation/ interconnection/ commissioning/ start-up
Term: 760 days from 23-Jun-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $18m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-007-03
Release: 23-Dec-03
Registration deadline: 07-May-04
Submission: 13-May-04
Registered bidders: 1.Industria del Hierro (ICA Fluor Daniel) 2.J Ray McDermott 3.Bosnor 4.Swecomex 5.ABB Mexico 6.Construcciones y Equipos Latinoamericanos (PROTEXA) 7.IZAR Construcciones Navales 8.Kiewit Offshore Services 9.Odebrecht Oil & Gas Mexico 10.Shaw Mexican Holdings 11.Construccion Ingenieria y Montaje Integral (CIMISA) 12.Berry Contracting 13.Dragados Offshore 4.COMMISA 15.Evya 16.Technip Offshore 17.Turbinas Solar 18.Swath de Mexico 19.Siemens 20.CPI-Berwanger 21.Maritima Petroleo e Ingenieria de Mexico 22.Comfact Corporation
Offers disclosure: 21-May-04
Decision: 01-Jun-04
Swecomex-Condumex (parent company): $130million

16. PB-KU-S (Production)
Project: Production platform/ burner/ bridge to drilling PP-KU-S/ bridge to living-quarter HA-KU-S/ bridge & tripod to burner in KMZ field
Original scope: Engineering/ procurement/ fabrication/ loading/ transport/ installation/ interconnection/ commissioning/ start-up
Actual scope: Engineering/ procurement/ fabrication/ loading/ technical assistance for installation/ interconnection/ commissioning/ start-up
Term: 880 days from 12-Jul-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $18m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-008-03
Release: 23-Dec-03
Registration deadline: 28-May-04
Submission: 03-Jun-04
Registered bidders: 1.Swecomex 2.Bosnor 3.Dragados Offshore 4.Construccion Ingenieria y Montaje Integral (CIMISA) 5.Grupo Mexicano de Desarrollo (GMD) 6.ABB Mexico 7.Construcciones y Equipos Latinoamericanos (PROTEXA) 8.J Ray McDermott 9.Kiewit Offshore Services 10.Odebrecht Oil & Gas Mexico 11.Siemens 12.Shaw Mexican Holdings 13.Swath de Mexico 15.Dynamic Industries 16.Turbinas Solar 17.Constructora Bay de Mexico 18.Maritima Petroleo e Ingenieria de Mexico
Offers disclosure: 10-Jun-04
Decision: 01-Jul-04
Swecomex: $225million

15. PB-KU-A2 (Production)
Project: Production platform/ burner/ bridge to E-KU-A2 (to be tendered)/ bridge & tripod to burner in KMZ field
Original scope: Engineering/ procurement/ fabrication/ loading/ transport/ installation/ interconnection/ commissioning/ start-up
Actual scope: Engineering/ procurement/ fabrication/ loading/ technical assistance for installation/ interconnection/ commissioning/ start-up
Term: 760 days from 03-Aug-04
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $18m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575106-009-03
Release: 23-Dec-03
Registration deadline: 15-Jun-04
Submission: 21-Jun-04
Registered bidders: 1.Dragados Offshore 2.Swecomex 3.ABB Mexico 4.Construcciones y Equipos Latinoamericanos (PROTEXA) 5.J Ray McDermott 6.Kiewit Offshore Services 7.Odebrecht Oil & Gas Mexico 8.Construccion Ingenieria y Montaje Integral (CIMISA) 9.Shaw Mexican Holdings 10.Constructora Bay de Mexico 11.Siemens 12.Turbinas Solar 13.Bosnor 14.Swath de Mexico 15.Maritima Petroleo e Ingenieria de Mexico 16.GIMSA Construcciones Industriales (TRIBASA)
Offers disclosure: 29-Jun-04
Decision: 16-Jul-04
Dragados Offshore de Mexico $185million

13/14. SINAN-A/B (8L-Drill)
Scope: Engineering/ procurement/ construction/ loading
Term/ field/ location: 450 days from 11-Mar-04/ Ku-Maloob-Zaap/ Bay of Campeche
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $5.5m+
Subcontracts allowed: Engineering/ rolling/ cranes/ weighing/ non destructive testing
Bid follow-up:
Ref: 18575106-006-03
Release: 02-Dec-03
Top bidders [Clarifications]{Attendances}:
1. Bay de Mexico [112]{2} 2.ICA Fluor Daniel [55]{1} 3.Bosnor [48]{2} 4.Evya [34]{2} 5.Construcciones y Equipos Latinoamericanos (PROTEXA) [39]{1} 6.Swecomex [25]{1} 7.Comercializacion Internacional de Tampico [19]{2} 8.Dragados Offshore Mexico [12]{2} 9.Construccion Ingenieria y Montaje Integral (CIMISA) [12]{2} 10.Construcciones Mecanicas de Monclova (COMMSA/GIMSA) [1]{0}
Submission: 30-Jan-04
Offers disclosure: 11-Feb-04
Decision: 23-Feb-04
Construccion Ingenieria y Montaje Integral (CIMISA) $43million
(Updated 27-Feb-04)

12. Lobina-1 (Gathering)
Scope: Engineering/ procurement/ construction/ installation
Term/ field/ location: 331 days from 22-Mar-04/ Lobina/ Bay of Campeche
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $3m+
Subcontracts allowed: Engineering/ x-ray inspection/ transport/ installation/ certification
Bid follow-up:
Ref: 18575106-003-03
Release: 18-Nov-03
Registered bidders: 1.Construcciones Mecanicas de Monclova (COMMSA/GIMSA) 2.ICA Fluor Daniel 3.Shaw Mexican Holdings 4.ABB Mexico 5.Construcciones y Equipos Latinoamericanos (PROTEXA) 6.Evya 7.Industria del Hierro (ICA) 8.BBI 9.Stolt Offshore
Submission: 10-Feb-04
Offers disclosure: 20-Feb-04
Decision: 02-Apr-04
Shaw Mexican Holdings $15.5million
(Updated 02-Apr-04)

10/11. SINAN-C&D (8L-Drill)
Scope: Engineering/ procurement/ construction/ loading
Term/ field/ location: 450 days from 16-Jan-04/ Ku-Maloob-Zaap/ Bay of Campeche
Contracts: Unit prices
Down payment: n/a
Payments: 20 days after invoicing procedures
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $6.75m+
Subcontracts allowed:
Bid follow-up:
Ref: 18575087-017-03
Release: 02-Oct-03
Registered bidders: 1.Industria del Hierro (ICA) 2.Bosnor 3.Construcciones Mecanicas de Monclova (COMMSA/GIMSA) 4.Construcciones y Equipos Latinoamericanos (PROTEXA) 5.Swecomex 6.Comercializadora Internacional de Tampico 7.EVYA 8.Constructora Bay de Mexico 9.Siemens 10.Dragados Offshore de Mexico 11.Honeywell 12.CIGSA Fabricacion 13.Invensys Systems Mexico 14.Emerson Project Management 15.Smar Mexico 16.Construtora Andrade Gutierrez 17.Saw Mexican Holdings 18.Hanover Compression Ltd Partnership 19.ICA Fluor Daniel 20.Energy Land & Sea Projects 21.Construccion Ingenieria y Montaje Integral (CIMISA)
Submission: 04-Dec-03
Offers disclosure: 12-Dec-03
Decision: 16-Jan-04
WINNER: Construcciones Mecanicas de Monclova (COMMSA/GIMSA) $44million
(Updated 22-Jan-04)

9. PP-KU-C (Drill)
Scope: Engineering/ procurement/ construction/ loading/ technical assistance for installation
Term/ field/ location: 525 days from 04-Oct-03/ Ku-Maloob-Zaap/ Gulf of Mexico
Contracts: Unit prices
Down payment: N/A
Payments: 20 days after invoicing procedures
Selection basis: Least offer among technically approved proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $5m+
Subcontracts allowed:
Engineering/ model/ non destructive testing/ weighing/ x-rays/ HAZOP-IPR
Bid follow-up:
Ref: 18575087-015-03
Release: 24-Jul-03
Registered bidders: 1.Swecomex 2.Evya 3.Bosnor 4.Construcciones y Trituraciones 5.Smar Mexico 6.Industria del Hierro (ICA) 7.Comercializacion Internacional Tampico 8.Honeywell 9.CIGSA Fabricacion 10.Aasercath 11.Asociacion en Ingenieria Aplicada 12.ABC Ingenieria Integral 13.ACE Service 14.C-T CAD Ingenieria y Proyectos 15.Ingenieria Total y Construcciones 16.Bufete Constructor America 17.Emerson Process Management 18.Construcciones Mecanicas de Monclova (COMMSA)
Submission: 03-Sep-03
Offers disclosure: 11-Sep-03
Decision: 07-Oct-03
WINNER: Bosnor $37million
(Updated 09-Oct-03)

7/8. PP-Maloob-A&B (Drill)
Scope: Engineering/ procurement/ construction/ loading/ transport (CANCELED)/ technical assistance for installation
Name / term / field/ location:
1. PP-Maloob-A/ 560 days from 29-Sep-03/ Ku-Maloob-Zaap/ Gulf of Mexico
2. PP-Maloob-B/ 590 days from 29-Sep-03/ Ku-Maloob-Zaap/ Gulf of Mexico
Contracts: Unit prices
Payments: 20 days after invoicing procedures
Selection basis: Least offer among technically approved proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $5m+ per contract
Subcontracts allowed:
Engineering/ models/ non destructive testing/ XRays/ weighing/ transport (CANCELED)/ HAZOP/ IPR
Bid follow-up
Ref: 18575087-009-03
Release: 22-May-03
Registered bidders: 1.Swecomex 2.Bosnor 3.ICA Fluor Daniel 4.Emerson Process Management 5.Smar Mexico 6.Duro Felguera 7.Honeywell 8.Equipomex 9.Industria del Hierro 10.CIGSA Fabricacion 11.Promaquina 12.Sodes Mexico 13.Construcciones Mecanicas de Monclova (COMMSA) 14.Construcciones y Equipos Latinoamericanos 15.Constructora Bay de Mexico 16.Siemens 17.Izar Construcciones Navales 18.Invensys Systems Mexico 19.ABB Mexico
Submission: 21-Aug-03
Offers disclosure: 01-Sep-03
Decision: 12-Sep-03
WINNER: Swecomex $80.5million
(Updated 18-Sep-03)

6. Manik-A (Drill)
Scope: Engineering/ procurement/ construction/ loading/ transport (CANCELED)/ certification (CANCELED)
Term/ field/ location: 420 days from 22-Sep-03/ Abkatum/ Gulf of Mexico
Contracts: Unit prices
Payments: 20 days after invoicing procedures
Selection basis: Least offer among technically approved proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $5m+
Subcontracts allowed:
Engineering/ non destructive testing/ weighing/ transport (CANCELED)/ cerfification (CANCELED)
Bid follow-up:
Ref: 18575087-008-03
Release: 29-May-03
Registered bidders: 1.Swecomex 2.Bosnor 3.Smar Mexico 4.ICA Fluor Daniel 5.Duro Felguera 6.Honeywell 7.Industria del Hierro (ICA) 8.CIGSA Fabricacion 9.Constructora Bay de Mexico 10.Construcciones Mecanicas de Monclova 11.Construcciones y Equipos Latinoamericanos 12.Comercializacion Internacional de Tampico 13.Siemens 14.Izar Construcciones Navales
Submission: 06-Aug-03
Decision: 02-Sep-03
WINNER: Swecomex $33.5million
(Updated 03-Sep-03)

5. KU-A2 (Link)
Scope: Engineering/ procurement/ construction/ loading/ transport/ technical assistance for installation (Rev 12-Jun-03)/ testing/ start-up
Project: Ku-Maloob-Zaap
Location: Campeche/KUMAZA field/Gulf of Mexico
Term: 570 days from 20-Aug-03 (Rev 12-Jun-03)
Contract: Unit prices
Payments: 20 days after invoicing procedures
Selection basis: Least offer among technically approved proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $9.5m+ (Rev 12-Jun-03)
Subcontracts allowed: Engineering/ models/ testing/ XRays/ transport/ HAZOP/ IPR
Bid follow-up:
Ref: 18575087-002-03
Release: 10-Apr-03
Bidders: 1.Bufete Industrial 2.Detroit Diesel Allison de Mexico 3.ICA Fluor Daniel 4.Constructora Bay de Mexico 5.Emerson Process Management 6.Smar Mexico 7.Equipos y Servicios VICA 8.Dragados Offshore 9.Swecomex 10.Bosnor 11.Construcciones Mecanicas de Monclova 12.Odebrecht Oil & Gas Mexico 13.Trade Ingenieria y Proyectos 14.CIGSA Fabricacion 15.Honeywell Mexico 16.Invensys Systems Mexico 17.Construcciones y Equipos Latinoamericanos 18.Siemens
Decision: 08-Aug-03
WINNER: Construcciones Mecanicas de Monclova (COMMSA/GIMSA) $48million
(Updated 07-Aug-03)

3/4. MAY-A&B (Drill)
g. Drilling platforms MAY-A & B
Scope: Engineering/ procurement/ construction/ loading/ transport
Location: Campeche/Gulf of Mexico
Term: 462 days starting 18-Jul-03
Contract: Unit prices
Payments: 20 days after invoicing procedures
Selection basis: Least offer among technically approved proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $11m+
Subcontracts allowed: Engineering/ models/ testing/ weighing/ transport/ certification
Bid information
Ref: 18575087-001-03
Release: 12-Mar-03
Register deadline: 04-Jun-03 (Rev 20-May-03) (Done)
Site visit: N/A
1st Bidders meeting: 14-Apr-03 (Done)
2nd Bidders meeting: 23-Apr-03 (Done)
Submission: 10-Jun-03 (Rev 20-May-03) (Next event)
Offers disclosure: 17-Jun-03 (Rev 20-May-03)
Bid follow-up:
Registered bidders (not comprehensive):
1.Cigsa Fabricacion 2.Duro Felguera 3.ICA Fluor Daniel 4.Bosnor 5.Swecomex 6.Corporacion Janko 7.Edemtec 8.Odebrecht Oil & Gas Mexico 9.Trade Ingenieria y Proyectos 10.Integrated Power Systems 11.Equipos y Servicios Vica 12.Reymon de Mexico 13.Constructora Bay de Mexico 14.Construcciones Mecanicas Monclova 15.Dynamic Industries 16.Comercializadora Internacional de Tampico 17.Construcciones y Equipos Latinoamericanos 18.Talleres Navales del Golfo 19.J Ray McDermott
Decision: 01-Jul-03
WINNER: ICA Fluor Daniel $55million
(Updated 04-Jul-03)

2. Ixtal-A (8L-Gathering)
18575038-019-02/ Bay de Mexico

1. Lankahuasa-1 (Gathering)
d. Offshore well recovery platform Lankahuasa 1
Scope: Engineering-Procurement-Construction
Complex: Lankahuasa
Location: Offshore Poza Rica Veracruz
Term: 244 days
Selection basis: Least offer among technically approved proposals
Bidders profile:
Company/consortium
Combine equity: US$3.5m+
Bid information
Ref: 18575008-062-02
Release: 10-Oct-02
Site visit: 14-Oct-02
1st Bidders meeting: 16-Oct-02
2nd Bidders meeting: 23-Oct-02
Register by 06-Nov-02
Submission due: 12-Nov-02
Offers disclosure: 26-Nov-02
Bid follow-up:
Registered bidders (not comprehensive): 1.Bosnor 2.Construcciones Mecanicas Monclova 3.Promotora e Inversora ADISA 4.Comercializacion Internacional de Tampico 5.ICA Fluor Daniel 6.Constructora Bay de mexico 7.Construcciones y Equipos Latinoamericanos 8.Dragados Offshore 9.ABS Group Services Mexico
Decision:
WINNER: ICA Fluor Daniel
(Updated 31-Dec-02)


PEMEX EXPLORATION & PRODUCTION (PEP)

PLATFORM RELATED PROJECTS HISTORY

Liftboat leasing [AWARDED]
Project description
Scope: Support for termination, maintenance & data acquisition of marine wells/ Logistics, installation, dismantlement of modules, structures, units and equipment components for well dirilling & maintenance or for production facilities/ Depth of water 180'+/ Independent legs 250'+ no extensions allowed/ DGPS required
Location: GOM
Term: 548 days from 18.Feb.80 to 18.Aug.09
Contracts: Leasing
Down payment: n/a
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Bid follow-up:
Ref: 18575088-022-07
Release: 18.Oct.07
Site visit: n/a
1st clarification meeting: 05.Nov.07
2nd clarification meeting: 12.Nov.07
3rd clarification meeting: 16.Nov.07
4th clarification meeting: 21.Nov.07
Closing: 23.Nov.07
Submission & opening: 29.Nov.07
Ruling: 19.Dec.07
Finalizing: 08.Jan.07
Registered bidders (not comprehensive)
1.Third Ocean Vessel and Rig 2.Power Marine 3.Cotemar 4.Servicios Maritimos de Campeche 5.Iner Servicios 6. Nabors 7.Perforaciones Maritimas Mexicanas (Protexa) 8.Geomarex 9.Superior Energy Services 10.Todco
Status AWARDED
Ruling: 19.Dec.07
Atlantic Marine Services BV: $31million
Updated 19.Dec.07

Offshore recondition & maintenance (2) [AWARDED]
Project description
Scope: Recondition & maintenance of offshore platforms & process centers with a subsea vessel (CA)
Locations:
Office & yards in Ciudad del Carmen Campeche
Platforms: Campeche basin GOM
Term: 1826 days from 15.Jan.08
Contracts: Unit prices
Down payment: n/a
Local content: +10%
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $42m+
Subcontracts allowed: Inspection for non-destructive testing/ diving/ satellite positioning
Bid follow-up:
Ref: 18575108-052-07
Release: 09.Oct.07
Site visit: n/a
1st clarification meeting: 19.Oct.07
2nd clarification meeting: 09.Nov.07
3rd clarification meeting: 14.Nov.07
Deadline for questioning & 4th clarification meeting: 16.Nov.07
5th clarification meeting: 22.Nov.07
Closing: 22.Nov.07
Submission & opening: 28.Nov.07
Registered bidders (not comprehensive)
1.Servicios Maritimos de Campeche 2.Condux (Protexa) 3.Cotemar 4.Mantenimiento Marino de Mexico (Halliburton) 5.Oceanografia
Status AWARDED
Ruling: 18.Dec.07
Cotemar: $340million
Updated 19.Dec.07

Offshore recondition & maintenance (1) [AWARDED]
Project description
Scope: Recondition & maintenance of offshore platforms with a subsea vessel (SA)
Locations:
Office & yards in Ciudad del Carmen Campeche
Platforms: Campeche basin GOM
Term: 1826 days from 21.Dec.08
Contracts: Unit prices
Down payment: n/a
Local content: +10%
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $24m+
Subcontracts allowed: Inspection for non-destructive testing/ diving/ satellite positioning
Bid follow-up:
Ref: 18575108-057-07
Release: 18.Sep.07
Site visit: n/a
1st clarification meeting: 24.Sep.07
9th clarification meeting & closing: 31.Oct.07
Submission & opening: 06.Nov.07
Registered bidders (not comprehensive)
1.Cotemar 2.Mantenimiento Marino de Mexico (Halliburton) 3.Condux (Protexa) 4.Servicios Maritimos de Campeche 5.Subtec 6.Paredon 7.Oceanografia
Status AWARDED
Ruling: 23.Nov.07
Cotemar: $295million
Updated 07.Feb.08

Offshore maintenance works (5) [AWARDED]
Project description
Scope: Offshore maintenance work with a dynamic positioning vessel
Location: Campeche basin GOM
Term: 5yrs starting 01.Feb.08
Contracts: Unit prices
Down payment: n/a
Local content: +10%
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $21m+
Subcontracts allowed: Inspection for non-destructive testing/ diving/ satellite positioning
Bid follow-up:
Ref: 18575108-045-07
Release: 09.Oct.07
Site visit: n/a
1st clarification meeting: 22.Oct.07
2nd clarification meeting: 05.Nov.07
3rd clarification meeting: 13.Nov.07
4th clarification meeting: 23.Nov.07
5th clarification meeting & closing: 30.Nov.07
Submission & opening: 06.Dec.07
Ruling: 08.Jan.07
Finalizing: 01.Feb.07
Registered bidders (not comprehensive)
1.Condux (Protexa) 2.Servicios Maritimos de Campeche 3.Construcciones Integrales del Carmen 4.Oceanografia 5.Mantenimiento Marino de Mexico (Halliburton) 6.Diavaz 7.Cotemar 8.Subtec
Potential participants
CTM Campeche Construcciones
Status AWARDED
Ruling: 08.Jan.07
Oceanografia: $215million
Updated 18.Jan.08

Offshore maintenance works (4) [DECISION PENDING]
Project description
Scope: Offshore maintenance work with a dynamic positioning vessel
Location: Campeche basin GOM
Term: 5yrs starting 01.March.08
Contracts: Unit prices
Down payment: n/a
Local content: +10%
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $17m+
Subcontracts allowed: Inspection for non-destructive testing/ diving/ satellite positioning
Bid follow-up:
Ref: 18575108-044-07
Release: 21.Aug.07
Site visit: n/a
1st clarification meeting: 18.Sep.07
2nd clarification meeting: 26.Sep.07
5th clarification meeting: 16.Oct.07
6th clarification meeting: 25.Oct.07
7th clarification meeting: 07.Nov.07
8th clarification meeting: 16.Nov.07
9th clarification meeting & closing: 23.Nov.07
Submission & opening: 29.Nov.07
Registered bidders (not comprehensive)
1.Cotemar 2.CTM Campeche Construcciones 3.Servicios Maritimos de Campeche 4.Diavaz 5.Subtec 6.Condux (Protexa) 7.Global Offshore 8.Mexicana de Servicios Subacuaticos 9.Oceanografia 10.ARB Arendal 11.Construcciones Integrales del Carmen 12.TMM 13.CCC
Status SUBMITED
Updated 30.Nov.07/rev 18.Apr.08

Offshore installation works [AWARDED]
Project description
Scope: Installation & recovery of platforms/ installation of heavy equipment
Location: Campeche basin GOM
Term: 1826 days from 09.Apr.08 to 08.Apr.13
Contracts: Unit prices
Down payment: n/a
Local content: 10%
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $55m+
Subcontracts allowed: Inspection for non-destructive testing/ diving/ satellite positioning/ MEBI & METI
Bid follow-up:
Ref: 18575108-029-07
Release: 31.May.07
Site visit: n/a
1st clarification meeting: 29.Jun.07
5th clarification meeting: 31.Jul.07 (last)
Closing: 31.Jul.07
Submission & opening: 06.Aug.07
Registered bidders (not comprehensive)
1.Cotemar 2.Construcciones Integrales del Carmen 3.Global Offshore Mexico 4.Subtec 5.Diavaz 6.Oceanografia 8.Condux (Protexa)
Status AWARDED
Decision: 24.Jan.08
Oceanografia: $445million
Updated 25.Jan.08


PEMEX EXPLORATION & PRODUCTION (PEP)

MSC HISTORY

15. CHICONTEPEC II [AWARDED]
Project
Scope: Integrated works/services for expoitation of onshore oil fields
Location: Veracruz-Puebla
Contract
Commissioner: Pemex-PEP
Unit prices
Term: 4yrs
Selection basis: Lowest price bid for compliant proposals
Bidders profile
Company/consortium
Combine equity: $43+m
Subcontracts allowed:
Bid follow-up
Ref: 18575051-050-06
Release: 02.Jan.07
Site visit: 16.Jan.07
1st clarification meeting: 23.Jan.07
2nd clarification meeting: 02.Feb.07
3rd clarification meeting: 09.Feb.07
4th clarification meeting: 15.Feb.07
5th clarification meeting: 21.Feb.07
6th clarification meeting: 22.Feb.07
7th clarification meeting: 21.Mar.07
8th clarification meeting: 02.Apr.07 (last)
Closing: 02.May.07
Preliminary revision of proposal packages: 03.May.07
Submission & opening: 08.May.07
Registered bidders
1.D&S Petroleum 2.ICA Fluor Daniel 3.Industrial Perforadora de Campeche (IPC) 4.Servicios Integrales GSM (Carso) 5.Tradeco 6.Baker Hughes 7.Turbinas Solar 8.MI Drilling Fluids 9.Dowell Schlumberger 10.Halliburton 11.Oilpatch Enterprises
Potential participants
Vetco Gray, ABB, Emerson Process Management
Status AWARDED
Decision: 13.Jun.07
DOWELL SCHLUMBERGER DE MEXICO: $1395million
Updated 25.Jun.07

14. BLOCK EURO [VOID]
Project
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos basin
Contract
Commissioner: Pemex-PEP
Unit prices
Term: 15yrs starting 02.May.07
Selection basis: Lowest price bid for compliant proposals
Bidders profile
Company/consortium
Combine equity: $14+m
Subcontracts allowed:
Any activity but project management
Bid follow-up
Ref: 18575110-036-06
Release: 10.Aug.06
Site visit: 24.Aug.06
7th clarification meeting: 12.Jan.07
8th clarification meeting: 26.Jan.07
9th clarification meeting: 15.Feb.07
10th clarification meeting: 21.Feb.07
Deadline for registration: 28.Feb.07
Submission & opening: 06.Mar.07
Decision: 06.Mar.07
Registered bidders
1.Repsol 2.Swecomex 3.Tecpetrol (Techint) 4.PTD (Petrobras) 5.Creatica 6.Cobra 7.EnCana 8.Petrodomos 9.GOIMSA
Potential participants
Global Drilling Fluids
Status
Tender declared VOID on 06.Mar.07
A new RFPs to be announced shortly
Updated 09.Mar.07

13. BLOCK MONCLOVA [AWARDED]
Project
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos basin
Contract
Commissioner: Pemex-PEP
Unit prices
Term: 15yrs starting 02.May.07
Selection basis: Lowest price bid for compliant proposals
Bidders profile
Company/consortium
Combine equity: $14+m
Subcontracts allowed: Any activity but project management
Bid follow-up
Ref: 18575110-035-06
Release: 10.Aug.06
Site visit: 23.Aug.06
7th clarification meeting: 11.Jan.07
8th clarification meeting: 24.Jan.07
9th clarification meeting: 14.Feb.07
10th clarification meeting: 20.Feb.07
Deadline for registration: 07.Mar.07
Submission & opening: 13.Mar.07
Decision: 22.Mar.07
Registered bidders
1.Repsol 2.PTD (Petrobras) 3.Construcciones Mecanicas de Monclova (COMMSA) 4.Creatica 5.Lewis 6.Minera Carbonifera Rio Escondido (GAN) 7.Coahuila Industrial Minera (GAN) 8.Monclova Pirineos Gas 9.EnCana 10.Perforadora Central
Status AWARDED
Construcciones Mecanicas de Monclova (COMMSA): $440million
Updated 23.Mar.07

12 BLOCK NEJO [AWARDED]
Project
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos basin
Contract
Commissioner: Pemex-PEP
Unit prices
Term: 15yrs starting 02.May.07
Selection basis: Lowest price bid for compliant proposals
Bidders profile
Company/consortium
Combine equity: $14+m
Subcontracts allowed: Any activity but project management
Bid follow-up
Ref: 18575110-034-06
Release: 10.Aug.06
Site visit: 22.Aug.06
7th clarification meeting: 10.Jan.07
8th clarification meeting: 22.Jan.07
9th clarification meeting: 13.Feb.07
10th clarification meeting: 19.Feb.07
Deadline for registration: 21.Feb.07
Submission & opening: 27.Feb.07
Decision: 05.Mar.07
Registered bidders (not comprehensive)
1.Repsol 2.Cobra 3.PTD (Petrobras) 4.Tecpetrol (Techint) 5.Swecomex 6.EnCana 7.Perforadora Central
Status AWARDED
Grupo Cobra (es): $930million
Updated 09.Mar.07

11. PANDURA-ANAHUAC
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos basin
Term: 15yrs from 14.Jan.05
Contract: Unit prices
Down payment: n/a
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium
Combine equity: $10+m
Subcontracts allowed: Any activity but contract/project management
Bid follow-up:
Ref: 18575008-060-04
Release: 29.Jul.04
Submission: 26.Oct.04
Registered bidders: 1.Industrial Perforadora de Campeche (IPC) 2.CNPC Services Venezuela Ltd 3.Monterrey Services and Technology 4.Constructora y Perforadora Latina 5.Itera International Energy Corporation 6.Halliburton de Mexico
Decision: 26.Oct.04
WINNER: Industrial Perforadora de Campeche (Mx) - Desarrollo y Servicio Petrolero (Mx)/ $900million/ 15yrs
(Updated 27.Oct.04)

10. RICOS
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos basin
Term: 15yrs from 14.Jan.05
Contract: Unit prices
Down payment: n/a
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium
Combine equity: $10+m
Subcontracts allowed: Any activity but contract/project management
Bid follow-up:
Ref: 18575008-061-04
Release: 29.Jul.04
1st Bidders meeting: 07.Sep.04
2nd Bidders meeting: 22.Sep.04
3rd Bidders meeting: 05.Oct.04
4th Bidders meeting: 13.Oct.04
5th Bidders meeting: 25.Oct.04 (next event)
Registration deadline: 03.Nov.04
Submission: 09.Nov.04
Registered bidders: 1.Constructora y Perforadora Latina 2.Dowell Schlumberger de Mexico 3.Industrial Perforadora de Campeche (IPC) 4.Itera International Energy Corporation 5.Monterrey Services & Technology
Offers disclosure: 11.Nov.04
Decision: 08.Feb.05/ VOID
(Updated 14.Oct.04)

9. MONCLOVA
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos basin
Term: 15yrs from 21.Jan.05
Contract: Unit prices
Down payment: n/a
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium
Combine equity: $5+m
Subcontracts allowed: Any activity but contract/project management
Bid follow-up:
Ref: 18575008-064-04
Release: 17.Aug.04
1st Bidders meeting: 06.Oct.04
2nd Bidders meeting: 18.Oct.04 (next event)
Registration deadline: 01.Dec.04
Submission: 07.Dec.04
Registered bidders: 1.Hullera Mexicana
Potential bidders: 1.Hoper's 2.FIEMSA 3.Technopet 4.CORROSA 5.COIMSA 6.GIMSA Montajes 7.Vetra Group 8.Benchmark Pipeline 9.Cody E Oil
Offers disclosure: 09.Dec.04
Decision: 15.Feb.06
WINNER: Hullera Mexicana (Mx) - Energy Milenium (Mx) - Andrews Technologies de Mexico (Mx)- Yuma Exploration (US) - Aries Operating (US)/ $456million/ 15yrs
(Updated 16.Feb.05)

8. PIRINEO
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos basin
Term: 15yrs from 21.Jan.05
Contract: Unit prices
Down payment: n/a
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium
Combine equity: $5+m
Subcontracts allowed: Any activity but contract/project management
Bid follow-up:
Ref: 18575008-065-04
Release: 17.Aug.04
1st Bidders meeting: 07.Oct.04
2nd Bidders meeting: 19.Oct.04 (next event)
Registration deadline: 08.Dec.04
Submission: 14.Dec.04
Registered bidders: 1.Hullera Mexicana
Potential bidders: 1.Andrews Technologies 2.CNPC Services Venezuela Ltd 3.Technopet 4.Benchmark Pipeline International 5.COIMSA 6.GIMSA Montajes 7.Vetra Group
Offers disclosure: 16.Dec.04
Decision: 24.Feb.05
WINNER: Constructora Industrial Monclova (Mx) - Materiales La Gloria (Mx) - Alianz Petroleum (Mx) - Steel Serv (Mx) - Suelopetrol (Ve) - NCT (Ve) - Petrotesting Colombia (Co)/ $645million/ 15 yrs
(Updated 25.Feb.05)

7. OLMOS
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos basin
Term: 15yrs from 20.Feb.04
Contract: Unit prices
Down payment: n/a
Selection basis: Lowest price bid from qualified proposals
Bidders profile:
Company/consortium
Combine equity: $5+m
Subcontracts allowed: Any activity but contract/project management
Bid follow-up:
Ref: 18575008-138-03
Release: 29.Jul.03
Registered bidders: 1.Lewis Energy Group
Submission: 14.Jan.04
Offers disclosure/decision: 15.Jan.04
WINNER: Lewis Energy Group $343.6million for 15yrs
(Updated 16.Jan.04)

6. FRONTERIZO
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos Basin
Term: 15yrs from 09.Jan.04
Contract: Unit prices
Down payment: n/a
Selection basis: Least offer among technically approved proposals
Bidders profile:
Company/consortium
Combine equity: $4+m
Subcontracts allowed: Any activity but contract/project management
Bid follow-up:
Ref: 18575008-137-03
Release: 29.Jul.03
Registered bidders: 1.Skanska Mexico 2.D&S Petroleum (sole qualified bidder) 3.Nexen Petroleum International 4.Amistad Energy Corp (disqualified)
Submission: 18.Nov.03
Offers disclosure/decision: 19.Nov.03
WINNER: Petroleo Brasileiro Mexico: Petrobras-Teikoku Oil Co-D&S Petroleum (Diavaz) $265million for 15yrs
(Updated 19.Nov.03)

5. RICOS
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos Basin
Term: 20yrs from 09.Jan.04
Contract: Unit prices
Down payment: n/a
Selection basis: Least offer among technically approved proposals
Bidders profile:
Company/consortium
Combine equity: $32.5+m
Subcontracts allowed: Any activity but contract/project management
Bid follow-up:
Ref: 18575008-128-03
Release: 17.Jul.03
Registered bidders: 1.Exxon Mobil 2.Totalfina Oil & Gas Mexique 3.Obrascon Huarte Lain 4.Repsol Exploracion
Submission: 12.Nov.03
VOID: No proposals submitted
(Updated 13.Nov.03)

4. CORINDON-PANDURA
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos Basin
Term: 20yrs from 09.Jan.04
Contract: Unit prices
Down payment: n/a
Selection basis: Least offer among technically approved proposals
Bidders profile:
Company/consortium
Combine equity: $71.5+m
Subcontracts allowed: Any activity but contract/project management
Bid follow-up:
Ref: 18575008-131-03
Release: 17.Jul.03
Registered bidders:1.Totalfina Oil and Gas Mexique 2.Repsol Exploracion/YPS 3.D&S Petroleum 4.Halliburton de Mexico 5.Techint
Submission: 05.Nov.03
VOID: No proposals submitted
(Updated 05.Nov.03)

3. MISION
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos Basin
Term: 20yrs from 09.Jan.04
Contract: Unit prices
Down payment: n/a
Selection basis: Least offer among technically approved proposals
Bidders profile:
Company/consortium
Combine equity: $10.5+m
Subcontracts allowed: Any activity but contract/project management
Bid follow-up:
Ref: 18575008-130-03
Release: 17.Jul.03
Registered bidders (not comprehensive): 1.Techint (sole actual bidder) 2.Repsol Exploracion/YPS 3.D&S Petroleum 4.Exxon Mobil Mexico 5.Totalfina Oil and Gas Mexique
Submission: 29.Oct.03
Offers disclosure/decision: 30.Oct.03
WINNER: Elina del Bajio: Elina-Techint-Industrial Perforadora de Campeche (IPC) $1,036million for 20yrs
(Updated 30.Oct.03)

2. CUERVITO
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos Basin
Term: 15yrs from 09.Jan.04
Contract: Unit prices
Down payment: n/a
Selection basis: Least offer among technically approved proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $9+m
Subcontracts allowed: Any activity but contract/project management
Bid follow-up:
Ref: 18575008-136-03
Release: 29.Jul.03
Registered bidders (not comprehensive): 1.Techint 2.D&S Petroleum (sole actual bidder) 3.Nexen Petroleum International
Submission: 22.Oct.03
Offers disclosure/decision: 23.Oct.03
WINNER: Petrobras/Teikoku Oil Co/D&S Petroleum (Diavaz) $260million for 15yrs
(Updated 23.Oct.03)

1. REYNOSA-MONTERREY
Scope: Gas field development/ infrastructure/ maintenance
Location: Burgos Basin
Term: 20yrs from 09.Jan.04
Contract: Unit prices
Down payment: n/a
Selection basis: Least offer among technically approved proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $43+m
Subcontracts allowed: Any activity but contract/project management
Bid follow-up:
Ref: 18575008-129-03
Release: 17.Jul.03
Registered bidders: 1.Repsol Exploracion/YPS (sole actual bidder) 2.Exxon Mobil Mexico 3.Totalfina Oil and Gas Mexique 4.Halliburton Mexico
Submission: 15.Oct.03
Offers disclosure: 16.Oct.03
Decision: 16.Oct.03
WINNER: Repsol Exploracion/YPS $2,437million for 20yrs
(Updated 16.Oct.03)


PEMEX GAS (PGPB)

MODULAR CRYOGENIC PROJECT [AWARDED]
Project
Description:
Modular cryogenic units 5 & 6, LPG/gasoline terminal, auxiliary services and integration to the gas process complex
Location: Burgos gas process complex in Reynosa, Tamaulipas
Scope: Basic & detailed engineering/ permitting/ procurement/ construction/ installation/ tests/ training/ commissioning/ As-built documentation
Contract
Commissioner: Pemex Gas PGPB (Govt)
Type: Mixed lump sum/unit prices
Term: 741 days starting 15.Jan.07
Selection basis: Best qualified amongst compliant proposals
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Comprehensive experience in at least two similar projects
ISO 9001 certified
Combine equity: $50m+
Bid follow-up
Ref: 18572039-001-06
Release: 19.Sep.06
Site visit: 26.Sep.06
8th clarification meeting: 16.Nov.06 (last)
Deadline for registration: 24.Nov.06
Submission & opening: 30.Nov.06
Decision: 22.Dec.06
Finalizing: 12.Jan.07
Registered bidders
1.Gutsa 2.ICA Fluor Daniel 3.Dragados 4.Lockwood Greene 5.Techint 6.Tubinas Solar 7.Inelectra 8.Skanska 9.Jantesa 10.Siemens 11.Areva T&D 12.Synercon 13.Invensys 14.Alcatel
Potential co-bidders
Elliot Co, Grupo R, ABB, Aritas
Status AWARDED
ICA Fluor Daniel: $275million
(Updated 26.Jan.07)


FEDERAL COMMISSION OF ELECTRICITY (CFE)

POWER PLANT HISTORY

HYDROELECTRIC LA YESCA (2nd round) [AWARDED]
Project
Capacity: 2x375 MW
Location: Jalisco-Nayarit
Term: 1720 days starting 17.Sep.07
Scope: Construction & financing (100%)
Contract: Mixed lump sum/unit prices
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $275m+
Local content: 5%
Subcontracts allowed:
Bid follow-up
Ref: 18164093-001-07
Release: 27.Feb.07
Site visit: 06.Mar.07
1st Clarification meeting: 29.Mar.07
7th Clarification meeting: 31.Jul.07
Closing: 01.Aug.07
Submission & opening: 07.Aug.07
Registered bidders
1.ICA 2.CARSO-IDEAL 3.Techint 4.Gutsa 5.Grupo Mexico 6.Impregilo 7.Voith Siemens 8.Prolec GE 9.La Peninsular 10.Construcciones y Trituraciones 11.Alstom 12.Va Tech Escher Wyss 13.Power Machines
Potential participants
GPPP, Cemex, ISA Ingenieria, PCM Concreto, Andrade Gutierrez
Actual proposals
1.ICA-Adisa-La Peninsular: $768million
2.CARSO-IDEAL: $808million
3.Impregilo-Techint: $856million
Ruling: 06.Sep.07
ICA-Adisa-La Peninsular: $768million
Status AWARDED
Updated 07.Sep.07
------------------------
1st-round RECORD
Registered bidders: 1.Mitsubishi 2.ISA 3.Gutsa 4.Power Machines de Mexico 5.Condux (Protexa) 6.ICA 7.GE 8.IDEAL 9.Techint 10.Sinohydro 11.Alstom 12.Mexico Constructora Industrial 13.Construcciones y Trituraciones 14.Obracon Huarte Lain 15.La Peninsular 16.Andrade Gutierrez 17.Tradeco 18.Va Tech Escher Wyss 19.Odebrecht 20.Carso Infraestructura
Proposals:
1.Sinohydro-Gutsa: 1053+197=$1250million
2.ICA-Adisa-CPH-Peninsular: 764+145=$909million
3.Impregilo-Techint: 678+127=$805million
Ruling:
Offers 1 & 2 higher than approved budget: $837million
Offer 3 did not comply with technical requirements
Tender declared VOID on 01.Nov.06

CC-SOLAR POWER PLANT AGUA PRIETA II [VOID]
Project
Description: Combined cycle plant formed by 2/3 gas turbogenerators with steam generators and auxiliary systems, one steam turbogenerator with auxiliary systems, one air condensator and complementary equipment. Also a solar camp to generate steam for the combined cycle. And the interconnection with a 230 kV substation.
Gas capacity: 535.64 MW +/- 15% (summer conditions)
Solar capacity: 24 MW
Scope: Design/ engineering/ procurement/ construction/ installation/ tests/ training/ commissioning
Location: Sonora
Contract
Commissioner: CFE (Govt)
Type: Lump sum
Term: 859 days starting 26.Sep.07
Financing: 100% gas capacity by contractor
Donation: $49.35million for 100% solar capacity by GEF-World Bank
Payment/milestone: Bid offer/ Provisional acceptance by CFE: 01.Feb.10
Selection basis: Best qualified amongst compliant proposals
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $100m+
Local content: 16%
Subcontracts allowed: Design/ engineering/ construction/ commissioning
Bid follow-up
Ref: 18164093-022-06
Release: 29.Aug.06
Site visit: 06.Sep.06
1st clarification meeting: 04.Oct.06
12th clarification meeting: 05.Jul.07
13th clarification meeting: 19.Jul.07
14th clarification meeting: 31.Jul.07 (last)
Closing: 02.Aug.07
Submission & opening: 08.Aug.07
Registered bidders
1.Iberdrola 2.Abener 3.Isolux 4.Dragados 5.Mitsubushi 6.Sener 7.Man Ferrostaal 8.Siemens 9.Socoin 10.Cobra 11.GE 12.El Paso 13.Techint 14.Itochu 15.ICA Fluor Daniel
Status
Tender declared VOID on 08.Aug.06
A new RFPs to be announced shortly
Updated 10.Aug.07

NUCLEAR POWER PLANT LAGUNA VERDE (1st Fase) [AWARDED]
Project
Description: Renewal of units 1 & 2 (2x810 MW)
Scope: Design/ engineering/ procurement/ dismantlement/ construction/ installation/ tests/ training/ commissioning
Location: Veracruz
Term: 1392 days starting 01.Mar.07
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: $130m+
Local content: 10%
Subcontracting: Allowed
Contract
Type: Lump sum
Financing: 100% by contractor
Payments/milestones:
Unit 1: Provisional acceptance by CFE scheduled for 05.Jul.10
Unit 1: Full acceptance by CFE
Unit 2: Provisional acceptance by CFE scheduled for 20.Dec.10
Unit 2: Full acceptance by CFE
Selection basis: Lowest price bid from compliant proposals
Bid follow-up
Ref: 18164093-013-06
Release: 25.May.06
Deadline for 6th-questioning: 17.Nov.06
6th clarification meeting: 30.Nov.06 (last)
Closing: 13.Jan.07
Submission & opening: 19.Jan.07
Decision: 12.Feb.07
Finalizing: 28.Feb.07
Registered bidders
1.Siemens 2.Sener (es) 3.ICA Fluor Daniel 4.Techint 5.Alstom 6.GE 7.Iberdrola 8.Elecnor 9.Mitsubishi
Proposals
1.GE-Diamante: $951.5million
2.Siemens-Techint-Sener: $695million
3.Iberdrola-Alstom: $605million
Decision: 12.Feb.07
Finalizing: 28.Feb.07 (next)
Status AWARDED
Iberdrola Ingenieria y Consultoria Mexico - Iberdrola Ingenieria y Construccion - Alstom Mexicana: $605million
Updated 12.Feb.07

CC POWER PLANT NORTE [AWARDED]
Project
Commissioner: CFE (Govt)
Location: Durango
Capacity: 333-450 Mw
Scope: Engineering Construction Operation
Financing & Owning
Construction program:
739 days starting 24.May.07
Contract: External Power Producer
Term: 25 years
Local content: 25% Min
Selection basis
Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having
a free trade agreement with Mexico
Combine equity:
US$92m+ (local currency 1b+)
Bid follow-up
Ref: 18164093-015-05
Release: 15.Nov.05
Register deadline: 17.Oct.06
Submission: 23.Oct.06
Offers opening: 19.Jan.07
Decision: 05.Mar.07
Registered bidders
1.Hitachi 2.GE 3.Techint 4.Chubu 5.Siemens 6.Transalta 7.Electricite de France 8.Constructora Andrade Gutierrez 9.Itochu 10.Petrobras 11.Mitsubishi 12.Fenosa 13.Valladolid International Investments 14.Energia Azteca (Intergen) 15.Iberdrola 16.Mitsui 17.Prolec GE 18.ICA Fluor Daniel 19.Energia Termodurango 20.ABB
Status AWARDED
Union Fenosa Internacional: 0.6294 Pesos/kWh (DOF 15.May.07)
(Updated 09.Mar.07)

HYDROELECTRIC LA YESCA (1st round) [VOID]
Project
Capacity: 2x375 MW
Location: Jalisco-Nayarit
Term: 1691 days
Project start/finish: 13.Nov.06/30.Jun.11
Scope: Construction & financing (100%)
Contract: Mixed lump sum/unit prices
Bid follow-up
Ref: 18164093-011-06
Release: 18.May.06
12th Clarification meeting: 06.Oct.06 (last)
Submission & opening: 13.Oct.06
Registered bidders
1.Mitsubishi 2.ISA 3.Gutsa 4.Power Machines de Mexico 5.Condux (Protexa) 6.ICA 7.GE 8.IDEAL 9.Techint 10.Sinohydro 11.Alstom 12.Mexico Constructora Industrial 13.Construcciones y Trituraciones 14.Obracon Huarte Lain 15.La Peninsular 16.Andrade Gutierrez 17.Tradeco 18.Va Tech Escher Wyss 19.Odebrecht 20.Carso Infraestructura
Proposals
1.Sinohydro-Gutsa: 1053+197=$1250million
2.ICA-Adisa-CPH-Peninsular: 764+145=$909million
3.Impregilo-Techint: 678+127=$805million
Ruling
Offers 1 & 2 higher than approved budget: $837million
Offer 3 did not comply with technical requirements
Status
Tender declared VOID on 01.Nov.06
A new RFPs to be announced shortly
(Updated 02.Nov.06)

CC POWER PLANT BAJA CALIFORNIA (2nd round) [AWARDED]
Project
Capacity: 252.3 MW +/-15%
Scope: Engineering Procurement Construction & Financing
Construction program: 858 days starting 25.Oct.06
Location: Tijuana BC
Contract
Turn key-Lump sum
Commissioner: CFE (Govt)
Local content: +18%
Selection basis: Lowest price bid from compliant proposals
Bidders profile
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: US$55m+
Bid follow-up
Ref: 18164093-017-06
Release: 18.Jul.06
Submission & opening: 29.Aug.06
Decision: 27.Sep.06
Bidders
1.Isolux 2.Abener 3.Dragados 4.Itochu 5.GE 6.Siemens 7.Techint 8.Socoin
Winner
Isolux-Techint: $174million
(Updated 13.Oct.06)

COAL POWER PLANT PACIFICO [AWARDED]
Location: Lazaro Cardenas (Mexico West coast)
Capacity: 648 MW
Scope: Engineering Construction & Financing
Construction program: 1342 days from 31.May.06 to 01.Feb.10
Contract: Turn key-Lump sum
Local content: 15% Min
Selection basis: Lowest price bid from compliant proposals
Bidders profile:
Company/consortium from countries having a free trade agreement with Mexico
Combine equity: US$95m+
Bid follow-up:
Ref: 18164093-003-03
Release: 22.Jul.03
Registered bidders (not comprehensive): 1.Techint 2.ICA Fluor Daniel 3.Alstom Power Mexico 4.Skanska Mexico 5.Mitsubishi Corporation 6.Mitsui & Co 7.Dragados Proyectos Industriales de Mexico 8.Hitachi 9.Soluziona Tecnologias de Informacion 10.Siemens 11.Itochu Corporation 12.Credit Agricole Indosuez 13.Skoda Export 14.GE International 15.ABB Utilities 16.Construtora Andrade Gutierrez 16.ABB Mexico
Decision: 06.Dec.05
Mitsubishi Corporation - Carboelectrica Diamante: $611million
(Updated 06.Dec.05)

2. CC Power plant Mexicali II
Ref: 18164093-002-02/ Cancelled
3. CC Power plant Tamazunchale
18164093-001-03/ 30.Jun.04/ Iberdrola Mexico/ IPP/ 25yrs/ 839-1135 MW
5. CC Power plant Tuxpan V
18164093-013-02/ 17.Dec.03/ Mitsubishi Corporation-Kyushu Electric Power Co/ IPP/ 25yrs/ 431-527 MW
7. CC Power plant Valladolid III
18164093-032-02/ 14.Oct.03/ Mitsui & Co Ltd/ IPP/ 25yrs/ 430-525 MW
8. CC Power plant Altamira V
18164093-001-02/ 22.Oct.03/ Iberdrola Mexico/ IPP/ 25yrs/ 975 MW
9. Hydroelectric El Cajon
18164093-011-02/ 14.Mar.03/ Constructora Internacional de Infraestructura: ICA-Promotora e Inversora Adisa-La Peninsular Compania Constructora-EnergomachExport Power Machine/ $749.5million/ $0.0685/Kw-h/ 2x375 MW